SOLAR Β· MISOSolar project J619, St. Landry Parish County
Solar project J619, St. Landry Parish County is a 50.0 MW solar request withdrawn in the MISO interconnection queue, in St. Landry Parish County, Louisiana.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2016 (completed)
- Withdrawn / abandonedJan 2019 (project stopped here)
- ConsentedJun 2018 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J619
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Champagne 69kV Substation
- Location
- St. Landry Parish County, Louisiana
- Technology
- Solar: 50.0 MW
- Total requested
- 50.0 MW
- Study phase
- GIA
- Queue status
- Withdrawn
- Entered queue
- 9 May 2016
- Agreement signed
- 20 June 2018
- Proposed online date
- January 2018
- Withdrawn
- January 2019
Location
Marker shows the centre of St. Landry Parish County; the queue data does not give exact sites.
Power plants in Louisiana Β· Transmission lines in Louisiana
Other requests in St. Landry Parish County
- Solar project J1644, St. Landry Parish CountySolar Β· 150 MW Β· under construction
- Battery storage project J3840, St. Landry Parish CountyBattery storage Β· 300 MW Β· in study
- Battery storage project J4075, St. Landry Parish CountyBattery storage Β· 300 MW Β· in study
- Onshore wind project J3368, St. Landry Parish CountyOnshore wind Β· 200 MW Β· in study
- Solar project J2714, St. Landry Parish CountySolar Β· 162 MW Β· in study
- Onshore wind project J3394, St. Landry Parish CountyOnshore wind Β· 156 MW Β· in study
- Solar project J1832, St. Landry Parish CountySolar Β· 145 MW Β· built
- Battery storage project J3311, St. Landry Parish CountyBattery storage Β· 400 MW Β· withdrawn
- Solar project J1217, St. Landry Parish CountySolar Β· 200 MW Β· withdrawn
- Battery storage project J1236, St. Landry Parish CountyBattery storage Β· 50.0 MW Β· withdrawn