United States βΊ Grid βΊ Interconnection queues βΊ Louisiana
BATTERY STORAGE Β· MISOBattery storage project J1236, St. Landry Parish County
Battery storage project J1236, St. Landry Parish County is a 50.0 MW battery storage request withdrawn in the MISO interconnection queue, in St. Landry Parish County, Louisiana, connecting to CLECO POWER.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2019 (completed)
- Withdrawn / abandonedAug 2020 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J1236
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- CLECO POWER
- Connection point (POI)
- Ville Platte - West Form 230 kV Line Tap
- Location
- St. Landry Parish County, Louisiana
- Technology
- Battery: 50.0 MW
- Total requested
- 50.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA Complete; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 29 April 2019
- Proposed online date
- October 2022
- Withdrawn
- August 2020
Location
Marker shows the centre of St. Landry Parish County; the queue data does not give exact sites.
Power plants in Louisiana Β· Transmission lines in Louisiana
Other requests in St. Landry Parish County
- Solar project J1644, St. Landry Parish CountySolar Β· 150 MW Β· under construction
- Battery storage project J3840, St. Landry Parish CountyBattery storage Β· 300 MW Β· in study
- Battery storage project J4075, St. Landry Parish CountyBattery storage Β· 300 MW Β· in study
- Onshore wind project J3368, St. Landry Parish CountyOnshore wind Β· 200 MW Β· in study
- Solar project J2714, St. Landry Parish CountySolar Β· 162 MW Β· in study
- Onshore wind project J3394, St. Landry Parish CountyOnshore wind Β· 156 MW Β· in study
- Solar project J1832, St. Landry Parish CountySolar Β· 145 MW Β· built
- Battery storage project J3311, St. Landry Parish CountyBattery storage Β· 400 MW Β· withdrawn
- Solar project J1217, St. Landry Parish CountySolar Β· 200 MW Β· withdrawn
- Solar project J619, St. Landry Parish CountySolar Β· 50.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem