United States › Grid › Interconnection queues › Louisiana
SOLAR · MISOSolar project J2224, Iberville Parish County
Solar project J2224, Iberville Parish County is a 200 MW solar request in interconnection study in the MISO interconnection queue, in Iberville Parish County, Louisiana, connecting to ENTERGY LOUISIANA.
- PlanningQueued Aug 2021 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Oct 2025 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J2224
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ENTERGY LOUISIANA
- Connection point (POI)
- Derrick 230 kV
- Location
- Iberville Parish County, Louisiana
- Technology
- Solar: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA In Process; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 25 August 2021
- Proposed online date
- October 2025
Location
Marker shows the centre of Iberville Parish County; the queue data does not give exact sites.
Other requests in Iberville Parish County
- Gas project J1246, Iberville Parish CountyGas · 725 MW · agreement signed
- Solar project J1583, Iberville Parish CountySolar · 175 MW · agreement signed
- Replacing 464.5 MW Steam/Gas with 97.8 MW Steam; DOW ChemGas · 1,232 MW · in study
- Gas project J4138, Iberville Parish CountyGas · 805 MW · in study
- Gas project J4191, Iberville Parish CountyGas · 805 MW · in study
- Gas project J4190, Iberville Parish CountyGas · 707 MW · in study
- Gas project J4109, Iberville Parish CountyGas · 1,300 MW · withdrawn
- Gas project J4166, Iberville Parish CountyGas · 710 MW · withdrawn
- Solar project J1073, Iberville Parish CountySolar · 300 MW · withdrawn
- Solar project J567, Iberville Parish CountySolar · 202 MW · withdrawn
- Solar project J1099, Iberville Parish CountySolar · 200 MW · withdrawn
- Solar project J1668, Iberville Parish CountySolar · 194 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem