SOLAR Β· MISOSolar project J567, Iberville Parish County
Solar project J567, Iberville Parish County is a 202 MW solar request withdrawn in the MISO interconnection queue, in Iberville Parish County, Louisiana.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2016 (completed)
- Withdrawn / abandonedJul 2017 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J567
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Unknown
- Location
- Iberville Parish County, Louisiana
- Technology
- Solar: 202 MW
- Total requested
- 202 MW
- Study phase
- Feasibility
- Queue status
- Withdrawn
- Entered queue
- 6 May 2016
- Proposed online date
- April 2019
- Withdrawn
- July 2017
Location
Marker shows the centre of Iberville Parish County; the queue data does not give exact sites.
Power plants in Louisiana Β· Transmission lines in Louisiana
Other requests in Iberville Parish County
- Gas project J1246, Iberville Parish CountyGas Β· 725 MW Β· agreement signed
- Solar project J1583, Iberville Parish CountySolar Β· 175 MW Β· agreement signed
- Replacing 464.5 MW Steam/Gas with 97.8 MW Steam; DOW ChemGas Β· 1,232 MW Β· in study
- Gas project J4138, Iberville Parish CountyGas Β· 805 MW Β· in study
- Gas project J4191, Iberville Parish CountyGas Β· 805 MW Β· in study
- Gas project J4190, Iberville Parish CountyGas Β· 707 MW Β· in study
- Solar project J2224, Iberville Parish CountySolar Β· 200 MW Β· in study
- Gas project J4109, Iberville Parish CountyGas Β· 1,300 MW Β· withdrawn
- Gas project J4166, Iberville Parish CountyGas Β· 710 MW Β· withdrawn
- Solar project J1073, Iberville Parish CountySolar Β· 300 MW Β· withdrawn
- Solar project J1099, Iberville Parish CountySolar Β· 200 MW Β· withdrawn
- Solar project J1668, Iberville Parish CountySolar Β· 194 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem