🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Louisiana

SOLAR · MISO

Solar project J2180, Sabine Parish County

Solar project J2180, Sabine Parish County is a 250 MW solar request in interconnection study in the MISO interconnection queue, in Sabine Parish County, Louisiana, connecting to CLECO POWER.

Queue statusIn planning
  1. PlanningQueued Jul 2022 (current stage)
  2. ConsentedDec 2025 (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Aug 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J2180
Grid region
MISO (Midcontinent)
Utility / transmission owner
CLECO POWER
Connection point (POI)
Fisher
Location
Sabine Parish County, Louisiana
Technology
Solar: 250 MW
Total requested
250 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA In Process; Post GIA Status: Not Started
Queue status
Active
Entered queue
13 July 2022
Agreement signed
8 December 2025
Proposed online date
August 2027

Location

Marker shows the centre of Sabine Parish County; the queue data does not give exact sites.

Power plants in Louisiana · Transmission lines in Louisiana

Other requests in Sabine Parish County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem