Interconnection queue in Illinois — page 9

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown42374.6 GW
Active in queue74.6 GW423 requests
Agreement signed7,430 MW51 requests
Withdrawn670115.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

423 requests · page 9 of 9
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J2908, Morgan County
Solar
30.0 MWIn study Morgan, ILMISO Jul 20222023
Solar project AI1-119, Kendall County
Solar
28.8 MWIn study Kendall, ILPJM Sep 2022target 2026
Solar project AI2-410, Dekalb County
Solar
28.5 MWIn study Dekalb, ILPJM Mar 2023target 2026
Onshore wind project AI2-400, Bureau County
Onshore wind
25.0 MWIn study Bureau, ILPJM Mar 2023target 2025
Solar + storage project J1200, Putnam County
Solar + storage
24.2 MWAgreement signed Putnam, ILMISO Apr 2019target 2024
Solar project AI2-013, Grundy County
Solar
24.1 MWIn study Grundy, ILPJM Nov 2022target 2026
Solar project AI2-135, Mclean County
Solar
24.0 MWIn study Mclean, ILPJM Feb 2023target 2025
Solar project J3993, Wayne County
Solar
21.4 MWIn study Wayne, ILMISO Apr 2025target 2027
Nuclear project J4010, Dewitt County
Nuclear
21.0 MWIn study Dewitt, ILMISO Apr 2025target 2027
Calumet BESS
Battery storage
20.0 MWAgreement signed Cook, ILPJM Oct 2019target 2027
Rochelle Solar
Solar
20.0 MWAgreement signed Ogle, ILPJM Sep 2019target 2028
Kincaid PV
Solar
20.0 MWAgreement signed Christian, ILPJM Oct 2019target 2028
Solar + storage project J1199, Fulton County
Solar + storage
20.0 MWAgreement signed Fulton, ILMISO Apr 2019target 2023
Staley Solar
Solar
20.0 MWAgreement signed Kankakee, ILPJM Feb 2018target 2024
Wilmington Solar Energy Project
Solar + storage
19.9 MWAgreement signed Will, ILPJM Sep 2020target 2027
Solar project AI2-403, Dekalb County
Solar
19.5 MWIn study Dekalb, ILPJM Mar 2023target 2026
Solar project AI1-173, Stephenson County
Solar
16.0 MWIn study Stephenson, ILPJM Sep 2022target 2027
Solar project AI1-077, Mchenry County
Solar
15.8 MWIn study Mchenry, ILPJM Jul 2022target 2025
Onshore wind project J2189, Mcdonough County
Onshore wind
15.6 MWIn study Mcdonough, ILMISO Aug 2021target 2019
Battery storage project AH2-205, Cook County
Battery storage
10.0 MWIn study Cook, ILPJM Mar 2022target 2026
Aurora Battery Storage
Battery storage
10.0 MWPaused / redesign Will, ILPJM Oct 2020target 2028
Battery storage project AH2-206, Cook County
Battery storage
10.0 MWIn study Cook, ILPJM Mar 2022target 2026
Gas project AH1-567, Will County
Gas · University Park Energy, LLC
5.0 MWIn study Will, ILPJM Mar 2025target 2025
Page 9 of 9

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)