United States › Grid › Interconnection queues › Illinois
SOLAR · PJMSolar project AI2-135, Mclean County
Solar project AI2-135, Mclean County is a 24.0 MW solar request in interconnection study in the PJM interconnection queue, in Mclean County, Illinois, connecting to ComEd.
Queue statusIn planning
- PlanningQueued Feb 2023 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2025 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AI2-135
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- ComEd
- Connection point (POI)
- McLean 345 kV (CIR Increase)
- Location
- Mclean County, Illinois
- Technology
- Solar: 24.0 MW
- Total requested
- 24.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Active
- Entered queue
- 28 February 2023
- Proposed online date
- December 2025
Location
Marker shows the centre of Mclean County; the queue data does not give exact sites.
Other requests in Mclean County
- Twin Groves Storage IIBattery storage · 50.0 MW · agreement signed
- Twin Groves Storage IBattery storage · 50.0 MW · agreement signed
- Surplus; G876/G877Wind + storage · 400 MW · in study
- Onshore wind project J3991, Mclean CountyOnshore wind · 340 MW · in study
- Battery storage project AI1-024, Mclean CountyBattery storage · 300 MW · in study
- Onshore wind project J3681, Mclean CountyOnshore wind · 300 MW · in study
- Dawson SolarSolar · 300 MW · in study
- Battery storage project J4118, Mclean CountyBattery storage · 250 MW · in study
- Battery storage project AI1-023, Mclean CountyBattery storage · 200 MW · in study
- Onshore wind project J3566, Mclean CountyOnshore wind · 198 MW · in study
- Bright Stalk Generating FacilityOnshore wind · 150 MW · in study
- Bright Stalk Generating FacilitySolar · 150 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem