| Project | Capacity | Status |
|---|---|---|
| Onshore wind project G0954, Lincoln County Onshore wind |
350 MW | In study |
| Titus Low Carbon Ventures Solar 1 Solar · Vaquero Solar, LLC |
338 MW | In study |
| Solar project GEN-2023-015, Finney County Solar |
330 MW | In study |
| Battery storage project AJ1-011, Lake County Battery storage |
328 MW | In study |
| Solar project J1598, Calcasieu Parish County Solar |
325 MW | Agreement signed |
| Galadriel Battery storage |
318 MW | In study |
| Quaking Aspen Solar + storage |
318 MW | In study |
| Gas project 899771, Person County Gas · Duke Energy Progress, LLC |
313 MW | Under construction |
| Cowboy Solar + storage |
312 MW | In study |
| Bulldog Power (TEF - Due Diligence) Gas · Bulldog Power LLC |
311 MW | In study |
| Oak Tree Energy Storage Battery storage · Live Oak Energy Storage, LLC |
310 MW | In study |
| Mesquite Solar 6 Solar + storage |
309 MW | In study |
| Buffalo Prairie Storage Solar + storage · Buffalo Meadow Energy Center, LLC |
308 MW | In study |
| Jackrabbit Power Bank Battery storage |
308 MW | In study |
| Haute Stockage Battery storage |
307 MW | Paused / redesign |
| Beaujolais BESS Battery storage |
307 MW | Paused / redesign |
| Cuchillas BESS Solar + storage · Gransolar Texas Two |
307 MW | In study |
| Green Palms Solar |
307 MW | In study |
| Laurel Wind Energy Center Onshore wind · LAUREL ENERGY CENTER, LLC |
307 MW | Agreement signed |
| Wolf Hollow III Gas · Wolf Hollow II Power LLC |
306 MW | In study |
| Serenity Solar |
305 MW | In study |
| Gosford Solar Storage Solar |
305 MW | In study |
| Panhandle Flagship Solar 2 Solar + storage · Panhandle Solar Group Operating Company LLC |
304 MW | Agreement signed |
| WOE Gyp King Wind Onshore wind · KSK Wind Farm 1, LLC |
304 MW | Paused / redesign |
| Twinkle Battery storage |
304 MW | In study |
| NavBoot BESS Battery storage · Navboot BESS LLC |
304 MW | Agreement signed |
| Whitewright Solar 2 Solar · SunWR, LLC |
302 MW | In study |
| Amerada Solar Solar + storage · Amerada Solar, LLC |
302 MW | In study |
| Riverbend Solar SLF Solar + storage · Riverbend Renewables, LLC |
302 MW | In study |
| Rubicon Power BESS Battery storage · Rubicon Power LLC |
301 MW | In study |
| Acker BESS Battery storage · Ogallala BESS LLC |
301 MW | Agreement signed |
| Solar project G0866, Sherman County Solar |
300 MW | In study |
| Battery storage project GEN-2022-139, Harrison County Battery storage |
300 MW | In study |
| Onshore wind project Q497, Navajo County Onshore wind |
300 MW | In study |
| Solar + storage project 2023-G11, Cochise County Solar + storage |
300 MW | In study |
| Onshore wind project G0872, Garfield County Onshore wind |
300 MW | In study |
| Solar + storage project AI2-443, Greene County Solar + storage |
300 MW | In study |
| Solar project GEN-2023-099, Jackson County Solar |
300 MW | In study |
| Solar + storage project G0865, Sherman County Solar + storage |
300 MW | In study |
| Onshore wind project G0918, Lane County Onshore wind |
300 MW | In study |
| Other project G0924, Walla Walla County Other |
300 MW | In study |
| Solar + storage project 2023-G17, Mohave County Solar + storage |
300 MW | In study |
| Other project G0925, Walla Walla County Other |
300 MW | In study |
| Gas project PIS040, Utah County Gas |
300 MW | In study |
| Onshore wind project G0973, Mason County Onshore wind |
300 MW | In study |
| Solar + storage project 9, Grant County Solar + storage |
300 MW | In study |
| Onshore wind project GEN-2023-107, Finney County Onshore wind |
300 MW | In study |
| AW300S Solar |
300 MW | Agreement signed |
| Other project G0923, Walla Walla County Other |
300 MW | In study |
| Solar + storage project G1047, Grant County Solar + storage |
300 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)309 · 110.9 GW
- ERCOT (Texas)356 · 76.0 GW
- CAISO (California)107 · 53.4 GW
- Southeast (non-ISO utilities)210 · 24.0 GW
- SPP (Southwest Power Pool)82 · 15.1 GW
- PJM (Mid-Atlantic, Midwest)156 · 14.6 GW
- MISO (Midcontinent)23 · 3,679 MW
- ISO-NE (New England)6 · 1,053 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)