Gas project 899771, Person County

Gas project 899771, Person County is a 313 MW gas request under construction in the Southeast interconnection queue, in Person County, North Carolina, connecting to Duke Energy Progress.

Queue statusUnder construction
  1. PlanningQueued Jun 2023 (completed)
  2. Consented (completed)
  3. Construction (current stage)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
899771
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Duke Energy Progress
Developer
Duke Energy Progress, LLC
Connection point (POI)
Roxboro Steam Station 230 kV Switchyard
Location
Person County, North Carolina
Technology
Gas: 313 MW
Total requested
313 MW
Service type
Network resource (NRIS)
Study phase
Construction - Pending
Queue status
Active
Entered queue
28 June 2023

Location

Marker shows the centre of Person County; the queue data does not give exact sites.

Power plants in North Carolina · Transmission lines in North Carolina

Other requests in Person County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem