🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Arizona

SOLAR + STORAGE · WEST

Solar + storage project 2023-G11, Cochise County

Solar + storage project 2023-G11, Cochise County is a 300 MW solar + storage request in interconnection study in the West interconnection queue, in Cochise County, Arizona, connecting to WAPA Desert Southwest Region.

Queue statusIn planning
  1. PlanningQueued Aug 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
2023-G11
Grid region
West (non-ISO utilities)
Utility / transmission owner
WAPA Desert Southwest Region
Connection point (POI)
Apache – Adams Tap 115kV
Location
Cochise County, Arizona
Technology
Solar: 300 MW · Battery
Total requested
300 MW
Queue status
Active
Entered queue
30 August 2023
Proposed online date
December 2028

Location

Marker shows the centre of Cochise County; the queue data does not give exact sites.

Power plants in Arizona · Transmission lines in Arizona

Other requests in Cochise County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem