ONSHORE WIND Β· WEST

Onshore wind project 168, Cochise County

Onshore wind project 168, Cochise County is a 300 MW onshore wind request withdrawn in the West interconnection queue, in Cochise County, Arizona, connecting to Tucson Electric Power Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2024 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
168
Grid region
West (non-ISO utilities)
Utility / transmission owner
Tucson Electric Power Company
Connection point (POI)
Greenlee-Winchester 345kV Transmission Line
Location
Cochise County, Arizona
Technology
Wind: 300 MW
Total requested
300 MW
Service type
NRIS and ERIS
Queue status
Withdrawn
Entered queue
29 April 2024
Proposed online date
December 2030

Location

Marker shows the centre of Cochise County; the queue data does not give exact sites.

Power plants in Arizona Β· Transmission lines in Arizona

Other requests in Cochise County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem