United States › Grid › Interconnection queues › Arizona

SOLAR + STORAGE · WEST

Solar + storage project 145, Cochise County

Solar + storage project 145, Cochise County is a 300 MW solar + storage request in interconnection study in the West interconnection queue, in Cochise County, Arizona, connecting to Tucson Electric Power Company.

Queue statusIn planning
  1. PlanningQueued Dec 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
145
Grid region
West (non-ISO utilities)
Utility / transmission owner
Tucson Electric Power Company
Connection point (POI)
Winchester 345 kV substation
Location
Cochise County, Arizona
Technology
Solar: 300 MW · Battery
Total requested
300 MW
Service type
Network resource (NRIS)
Queue status
Active
Entered queue
14 December 2022
Proposed online date
December 2025

Location

Marker shows the centre of Cochise County; the queue data does not give exact sites.

Power plants in Arizona · Transmission lines in Arizona

Other requests in Cochise County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem