United States › Grid › Interconnection queues › Arizona

ONSHORE WIND · WEST

Onshore wind project Q497, Navajo County

Onshore wind project Q497, Navajo County is a 300 MW onshore wind request in interconnection study in the West interconnection queue, in Navajo County, Arizona, connecting to Arizona Public Service.

Queue statusIn planning
  1. PlanningQueued Mar 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
Q497
Grid region
West (non-ISO utilities)
Utility / transmission owner
Arizona Public Service
Connection point (POI)
Cholla-Pinnacle peak 345 kV line
Location
Navajo County, Arizona
Technology
Wind: 300 MW
Total requested
300 MW
Service type
Network resource (NRIS)
Study phase
Transitional Cluster: Phase 3 (Re-Study)
Queue status
Active
Entered queue
21 March 2023
Proposed online date
October 2027

Location

Marker shows the centre of Navajo County; the queue data does not give exact sites.

Power plants in Arizona · Transmission lines in Arizona

Other requests in Navajo County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem