United States › Grid › Interconnection queues
OCTARY USA · INTERCONNECTION QUEUESWithdrawn queue requests in the USA (2020 requests) — page 6
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Onshore wind project GEN-2020-053, Newton County Onshore wind |
240 MW | Withdrawn / abandoned |
| Onshore wind project G0658, Klamath County Onshore wind |
239 MW | Withdrawn / abandoned |
| Onshore wind project 1192, Klamath County Onshore wind |
239 MW | Withdrawn / abandoned |
| Powwow Solar + storage |
236 MW | Withdrawn / abandoned |
| Robin 3 Solar + storage |
235 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2020-021, Sioux County Onshore wind |
235 MW | Withdrawn / abandoned |
| BRP Pular BESS Battery storage · BRP Pular BESS LLC |
233 MW | Withdrawn / abandoned |
| Alba Solar + storage |
233 MW | Withdrawn / abandoned |
| Allium Solar + storage |
229 MW | Withdrawn / abandoned |
| Allegro Hybrid Solar Solar + storage |
227 MW | Withdrawn / abandoned |
| Solar project GI-94, Jasper County Solar |
225 MW | Withdrawn / abandoned |
| Solar project AG1-528 Solar |
225 MW | Withdrawn / abandoned |
| Solar + storage project 380, Cascade County Solar + storage |
225 MW | Withdrawn / abandoned |
| Solar project AF2-355, Madison County Solar · AEUG Richmond Solar, LLC |
225 MW | Withdrawn / abandoned |
| Garrard Solar Solar · PJM Solar Devco I, LLC |
222 MW | Withdrawn / abandoned |
| Solar + storage project IC-852, Marengo County Solar + storage |
220 MW | Withdrawn / abandoned |
| Solar project IC-911, Miller County Solar |
220 MW | Withdrawn / abandoned |
| Solar + storage project IC-849, Houston County Solar + storage |
220 MW | Withdrawn / abandoned |
| Solar project AF2-217, Union County Solar |
220 MW | Withdrawn / abandoned |
| Solar + storage project IC-855, Dallas County Solar + storage |
220 MW | Withdrawn / abandoned |
| Solar + storage project IC-853, Henry County Solar + storage |
220 MW | Withdrawn / abandoned |
| Solar + storage project IC-848, Autauga County Solar + storage |
220 MW | Withdrawn / abandoned |
| Gas project IA-PNM-2020-03, San Juan County Gas |
216 MW | Withdrawn / abandoned |
| Beech Hollow Solar Solar |
215 MW | Withdrawn / abandoned |
| Onshore wind project AF2-267, Stephenson County Onshore wind |
211 MW | Withdrawn / abandoned |
| Solar project AG1-224, Fayette County Solar · RUSH SOLAR PROJECT II, LLC |
210 MW | Withdrawn / abandoned |
| Cottage Meadow Storage Other · KCE TX 18, LLC |
209 MW | Withdrawn / abandoned |
| Cayuga Solar Solar · sPower Development Company, LLC |
207 MW | Withdrawn / abandoned |
| Neptune Solar Solar · Matagorda Solar LLC |
206 MW | Withdrawn / abandoned |
| Egret Hill Storage Other · Coyote Crossing LLC |
206 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2020-018, Sully County Onshore wind |
205 MW | Withdrawn / abandoned |
| Galactic Solar Solar · UKA North America, LLC |
205 MW | Withdrawn / abandoned |
| Foxglove Hybrid Solar Solar + storage |
205 MW | Withdrawn / abandoned |
| Torana Hybrid Solar Solar + storage |
205 MW | Withdrawn / abandoned |
| Thunderbird Solar SLF Solar · Thunderbird Solar, LLC |
204 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
204 MW | Withdrawn / abandoned |
| Flagtail Batt Other · Flagtail LLC |
204 MW | Withdrawn / abandoned |
| Austin Es Battery storage |
204 MW | Withdrawn / abandoned |
| BRP Lyra BESS Other · BRP Lyra BESS LLC |
203 MW | Withdrawn / abandoned |
| Corbin Grid BESS Other · Corbin Grid, LLC |
203 MW | Withdrawn / abandoned |
| Wekiva Grid Battery storage · Wekiva Grid, LLC |
203 MW | Withdrawn / abandoned |
| Sibyl Energy Storage Other · WattBridge Energy, LLC |
202 MW | Withdrawn / abandoned |
| Topaz Energy Storage Other · WattBridge Energy, LLC |
202 MW | Withdrawn / abandoned |
| Battery storage project GEN-2020-023, Garfield County Battery storage |
202 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2020-016, Tillman County Onshore wind |
202 MW | Withdrawn / abandoned |
| Clybourn Solar Solar · Leeward Renewable Energy Development, LLC |
202 MW | Withdrawn / abandoned |
| Milwaukee Solar Solar · Leeward Renewable Energy Development, LLC |
202 MW | Withdrawn / abandoned |
| BRP Kailas BESS Battery storage · BRP Kailas BESS LLC |
201 MW | Withdrawn / abandoned |
| Raoul Solar Solar · Leeward Renewable Energy Development, LLC |
201 MW | Withdrawn / abandoned |
| Elston Solar Solar · Leeward Renewable Energy Development, LLC |
201 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- PJM (Mid-Atlantic, Midwest)719 · 47.9 GW
- CAISO (California)107 · 46.6 GW
- West (non-ISO utilities)184 · 38.3 GW
- Southeast (non-ISO utilities)178 · 30.1 GW
- MISO (Midcontinent)195 · 27.2 GW
- NYISO (New York)129 · 25.5 GW
- SPP (Southwest Power Pool)60 · 10.4 GW
- ERCOT (Texas)67 · 10.4 GW
- ISO-NE (New England)113 · 9,841 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)