Solar + storage project 380, Cascade County

Solar + storage project 380, Cascade County is a 225 MW solar + storage request withdrawn in the West interconnection queue, in Cascade County, Montana, connecting to NorthWestern Energy.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2020 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
380
Grid region
West (non-ISO utilities)
Utility / transmission owner
NorthWestern Energy
Connection point (POI)
Great Falls 230kV
Location
Cascade County, Montana
Technology
Solar: 225 MW Β· Battery
Total requested
225 MW
Service type
NRIS and ERIS
Study phase
Feasibility Study System Impact Study
Queue status
Withdrawn
Entered queue
3 June 2020
Proposed online date
January 2023

Location

Marker shows the centre of Cascade County; the queue data does not give exact sites.

Power plants in Montana Β· Transmission lines in Montana

Other requests in Cascade County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem