ONSHORE WIND · WESTOnshore wind project 23, Cascade County
Onshore wind project 23, Cascade County is a 9.0 MW onshore wind request built and operating in the West interconnection queue, in Cascade County, Montana, connecting to NorthWestern Energy.
Request details
- Queue ID
- 23
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- NorthWestern Energy
- Connection point (POI)
- Great Falls NW - Holter 100kV Line
- Location
- Cascade County, Montana
- Technology
- Wind: 9.0 MW
- Total requested
- 9.0 MW
- Service type
- Energy only (ERIS)
- Study phase
- Feasibility Study System Impact Study Facilities Study
- Queue status
- Operational
- Entered queue
- 15 August 2002
- Proposed online date
- February 2006
- Came online
- February 2006
Location
Marker shows the centre of Cascade County; the queue data does not give exact sites.
Other requests in Cascade County
- Hydro project 437, Cascade CountyHydro · 70.0 MW · in study
- Hydro project 49, Cascade CountyHydro · 23.0 MW · built
- Hydro project 301, Cascade CountyHydro · 12.0 MW · built
- Hydro project 371, Cascade CountyHydro · 4.0 MW · built
- Solar project 211, Cascade CountySolar · 3.0 MW · built
- Hydro project 398, Cascade CountyHydro · 2.0 MW · built
- Onshore wind project 410, Cascade CountyOnshore wind · 0.7 MW · built
- Solar + storage project 429, Cascade CountySolar + storage · 300 MW · withdrawn
- Gas project 7, Cascade CountyGas · 280 MW · withdrawn
- Gas project 53, Cascade CountyGas · 277 MW · withdrawn
- Coal project 32, Cascade CountyCoal · 268 MW · withdrawn
- Solar + storage project 380, Cascade CountySolar + storage · 225 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem