United States βΊ Grid βΊ Interconnection queues βΊ Missouri
SOLAR Β· SOUTHEASTSolar project GI-94, Jasper County
Solar project GI-94, Jasper County is a 225 MW solar request withdrawn in the Southeast interconnection queue, in Jasper County, Missouri, connecting to Associated Electric Cooperative, Incorporated.
Queue statusWithdrawn / abandoned
- PlanningQueued Dec 2020 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GI-94
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Associated Electric Cooperative, Incorporated
- Connection point (POI)
- Jasper-Morgan 345 kV
- Location
- Jasper County, Missouri
- Technology
- Solar: 225 MW
- Total requested
- 225 MW
- Service type
- Network resource (NRIS)
- Queue status
- Withdrawn
- Entered queue
- 1 December 2020
- Proposed online date
- August 2023
Location
Marker shows the centre of Jasper County; the queue data does not give exact sites.
Other requests in Jasper County
- Solar project GEN-2020-088, Jasper CountySolar Β· 150 MW Β· agreement signed
- Gas project GEN-2020-064, Jasper CountyGas Β· 64.0 MW Β· agreement signed
- Gas project ERAS-2025-034, Jasper CountyGas Β· 250 MW Β· in study
- Battery storage project GEN-2024-091, Jasper CountyBattery storage Β· 100 MW Β· in study
- Battery storage project GEN-2023-061, Jasper CountyBattery storage Β· 100 MW Β· in study
- Gas project GEN-2001-030, Jasper CountyGas Β· 50.0 MW Β· built
- Gas project GEN-2001-040, Jasper CountyGas Β· 50.0 MW Β· built
- Gas project GEN-2016-013, Jasper CountyGas Β· 10.0 MW Β· built
- Gas project GEN-2016-014, Jasper CountyGas Β· 10.0 MW Β· built
- Gas project GEN-2003-011, Jasper CountyGas Β· 600 MW Β· withdrawn
- Coal project GEN-2003-007, Jasper CountyCoal Β· 550 MW Β· withdrawn
- Solar project GEN-2017-189, Jasper CountySolar Β· 202 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem