πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Missouri

COAL Β· SPP

Coal project GEN-2003-007, Jasper County

Coal project GEN-2003-007, Jasper County is a 550 MW coal request withdrawn in the SPP interconnection queue, in Jasper County, Missouri, connecting to EDE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2003 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2003-007
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
EDE
Location
Jasper County, Missouri
Technology
Coal: 550 MW
Total requested
550 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
14 July 2003
Proposed online date
June 2009

Location

Marker shows the centre of Jasper County; the queue data does not give exact sites.

Power plants in Missouri Β· Transmission lines in Missouri

Other requests in Jasper County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem