πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί California

SOLAR + STORAGE Β· CAISO

Powwow

Powwow is a 236 MW solar + storage request withdrawn in the CAISO interconnection queue, in San Diego County, California, connecting to SDGE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2020 (completed)
  2. Withdrawn / abandonedMay 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1817
Grid region
CAISO (California)
Utility / transmission owner
SDGE
Connection point (POI)
Oceanside Tap - Stuart Tap 69kV (TL690C )
Location
San Diego County, California
Technology
Solar: 33.5 MW Β· Battery: 202 MW
Total requested
236 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
15 April 2020
Proposed online date
June 2022
Withdrawn
May 2021

Location

Marker shows the centre of San Diego County; the queue data does not give exact sites.

Power plants in California Β· Transmission lines in California

Other requests in San Diego County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem