Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 351 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Long Draw Energy Project
Solar · Turner/Ross Wind Development LLC
38.0 MWWithdrawn / abandoned ERCOT Mar 2011target 2015
Solar project AF2-127, Defiance County
Solar
38.0 MWWithdrawn / abandoned Defiance, OHPJM Feb 2020target 2022
Del Sur Solar
Solar
38.0 MWWithdrawn / abandoned Los Angeles, CACAISO Mar 2011target 2013
Dixie-Comstock Geothermal Project
Geothermal
38.0 MWWithdrawn / abandoned Churchill, NVCAISO Mar 2011target 2014
Other project 132808, Cumberland County
Other · Duke Energy Progress, LLC
38.0 MWWithdrawn / abandoned Cumberland, NCSoutheast Sep 2020
Solar project IC-1010, Macon County
Solar
38.0 MWWithdrawn / abandoned Macon, GASoutheast Jan 2022
Edwards Creek Geothermal Project
Geothermal
38.0 MWWithdrawn / abandoned Churchill, NVCAISO Mar 2011target 2014
Morrow Street Energy Storage
Battery storage · Morrow Street Storage 2, LLC
38.0 MWWithdrawn / abandoned Richmond, NYNYISO Jun 2021
Solar project J3767, Crawford County
Solar
38.0 MWWithdrawn / abandoned Crawford, INMISO Apr 2024target 2028
Geothermal project G0477, Deschutes County
Geothermal
38.0 MWWithdrawn / abandoned Deschutes, ORWest Sep 2012target 2015
Tungsten Mountain Geothermal Project
Geothermal
38.0 MWWithdrawn / abandoned Churchill, NVCAISO Mar 2011target 2013
Solar project AH1-532, Marion County
Solar
37.8 MWWithdrawn / abandoned Marion, KYPJM Sep 2021target 2025
Cabeza de Vaca
Solar · PREMIER ENGINEERING USA CORP
37.8 MWWithdrawn / abandoned Lamar, TXERCOT Dec 2021target 2026
Solar project 165980, Laurens County
Solar
37.5 MWWithdrawn / abandoned Laurens, SCSoutheast Mar 2020
Battery storage project Q258, Maricopa County
Battery storage
37.5 MWWithdrawn / abandoned Maricopa, AZWest Sep 2017target 2021
Jawbone Wind Energy Project
Onshore wind
37.4 MWWithdrawn / abandoned Kern, CACAISO May 2017target 2021
01 37MW Connell
Gas · Effective Energy Corporation
37.0 MWWithdrawn / abandoned Franklin, WAWest Aug 2001target 2002
Battery storage project J3187, Mason County
Battery storage
37.0 MWWithdrawn / abandoned Mason, ILMISO Aug 2022target 2024
02 37MW Franklin PUD,Franklin Riverview
Gas · Effective Energy Corporation
37.0 MWWithdrawn / abandoned Franklin, WAWest Aug 2001target 2002
Murphy 1
Solar
37.0 MWWithdrawn / abandoned Riverside, CACAISO Mar 2011target 2015
Biomass
Other
37.0 MWWithdrawn / abandoned Windsor, VTISO-NE May 2013target 2015
Solar + storage project AG2-605, Amherst County
Solar + storage
37.0 MWWithdrawn / abandoned Amherst, VAPJM Mar 2021target 2024
Onshore wind project J1767, Hancock County
Onshore wind
37.0 MWWithdrawn / abandoned Hancock, IAMISO Jun 2020target 2023
Gas project C09, Bergen County
Gas
37.0 MWWithdrawn / abandoned Bergen, NJPJM Feb 2000
Other project IA-PNM-2004-02, Torrance County
Other
37.0 MWWithdrawn / abandoned Torrance, NMWest Jul 2004target 2012
Solar project AF2-220, Pulaski County
Solar
37.0 MWWithdrawn / abandoned Pulaski, VAPJM Mar 2020target 2023
Solar project J3390, Miami County
Solar
37.0 MWWithdrawn / abandoned Miami, INMISO Apr 2024target 2027
Pala Canyon Renewable (Fka Pala Fallbrook Energy Center)
Solar + storage
37.0 MWWithdrawn / abandoned San Diego, CACAISO Apr 2015target 2017
Travis Kimbro BESS
Battery storage · Travis Kimbro BESS LLC
36.8 MWWithdrawn / abandoned Travis, TXERCOT Sep 2022target 2028
Palmer Renewable Energy
Other
36.7 MWWithdrawn / abandoned Hampden, MAISO-NE Aug 2008target 2020
Thor Solar
Solar · Blue Stone Renewable III
36.6 MWWithdrawn / abandoned Rensselaer, NYNYISO Sep 2024
Hydro project AG1-292, Beaver County
Hydro
36.6 MWWithdrawn / abandoned Beaver, PAPJM Sep 2020target 2023
Nightshade
Gas
36.4 MWWithdrawn / abandoned Contra Costa, CACAISO Apr 2021target 2027
Hydro project J324, Grant Parish County
Hydro
36.2 MWWithdrawn / abandoned Grant Parish, LAMISO Mar 2014target 2017
Solar project J3819, Madison County
Solar
36.1 MWWithdrawn / abandoned Madison, MSMISO Apr 2024target 2027
Hilltop Wind Energy
Onshore wind · GreenHunter Wind Energy
36.0 MWWithdrawn / abandoned ERCOT Jul 2008target 2050
Roundhouse Renewable
Gas · CRC Development, LLC
36.0 MWWithdrawn / abandoned Otsego, NYNYISO Jan 2006
Other project 119, Rosebud County
Other
36.0 MWWithdrawn / abandoned Rosebud, MTWest Jul 2010target 2013
Big Lake Windfarm
Onshore wind · Airtricity, Inc.
36.0 MWWithdrawn / abandoned ERCOT Nov 2007target 2050
Solar project AB2-090, Mecklenburg County
Solar
36.0 MWWithdrawn / abandoned Mecklenburg, VAPJM Apr 2016target 2018
Hydro project J2831, Natchitoches Parish County
Hydro
36.0 MWWithdrawn / abandoned Natchitoches Parish, LAMISO Sep 2022target 2027
Solar + storage project Q330, Yuma County
Solar + storage
36.0 MWWithdrawn / abandoned Yuma, AZWest Mar 2020target 2022
Gas project Z1-021, Defiance County
Gas
36.0 MWWithdrawn / abandoned Defiance, OHPJM Jun 2013target 2014
Solar project Q522, Maricopa County
Solar
36.0 MWWithdrawn / abandoned Maricopa, AZWest Mar 2023target 2026
Oceanside Energy Storage
Battery storage · EDF Renewables Development, Inc.
36.0 MWWithdrawn / abandoned Nassau, NYNYISO Feb 2021
Solar + storage project IA-PNM-2019-21, Santa Fe County
Solar + storage
36.0 MWWithdrawn / abandoned Santa Fe, NMWest Apr 2019target 2021
Other project 107, Orange County
Other · Masked
36.0 MWWithdrawn / abandoned Orange, FLSoutheast Feb 2011
Other project G814, Antrim County
Other
36.0 MWWithdrawn / abandoned Antrim, MIMISO May 2009target 2009
Gas project Z2-091, Butler County
Gas
36.0 MWWithdrawn / abandoned Butler, OHPJM Apr 2014target 2014
San Diego Wind #2 - Phase I
Onshore wind
36.0 MWWithdrawn / abandoned San Diego, CACAISO Feb 2004target 2008
Page 351 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)