πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Ohio

GAS Β· PJM

Gas project Z1-021, Defiance County

Gas project Z1-021, Defiance County is a 36.0 MW gas request withdrawn in the PJM interconnection queue, in Defiance County, Ohio, connecting to ATSI.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2013 (completed)
  2. Withdrawn / abandonedApr 2014 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
Z1-021
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ATSI
Connection point (POI)
Richland II 138kV
Location
Defiance County, Ohio
Technology
Gas: 36.0 MW
Total requested
36.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study
Queue status
Withdrawn
Entered queue
4 June 2013
Proposed online date
April 2014
Withdrawn
April 2014

Location

Marker shows the centre of Defiance County; the queue data does not give exact sites.

Power plants in Ohio Β· Transmission lines in Ohio

Other requests in Defiance County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem