United States βΊ Grid βΊ Interconnection queues βΊ Ohio
ONSHORE WIND Β· PJMOnshore wind project W4-006, Defiance County
Onshore wind project W4-006, Defiance County is a 150 MW onshore wind request withdrawn in the PJM interconnection queue, in Defiance County, Ohio, connecting to AEP.
Queue statusWithdrawn / abandoned
- PlanningQueued Nov 2010 (completed)
- Withdrawn / abandonedApr 2012 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- W4-006
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- S. Hicksville-Lockwood Road 138kV
- Location
- Defiance County, Ohio
- Technology
- Wind: 150 MW
- Total requested
- 150 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 19 November 2010
- Proposed online date
- December 2014
- Withdrawn
- April 2012
Location
Marker shows the centre of Defiance County; the queue data does not give exact sites.
Other requests in Defiance County
- Mark Center Solar ProjectSolar Β· 60.0 MW Β· agreement signed
- Mark Center Solar ProjectSolar Β· 49.9 MW Β· agreement signed
- Richland Power PlantGas Β· 5.0 MW Β· built
- Gas project Z1-018, Defiance CountyGas Β· 591 MW Β· withdrawn
- Solar project AH1-770, Defiance CountySolar Β· 184 MW Β· withdrawn
- Solar project AF2-209, Defiance CountySolar Β· 140 MW Β· withdrawn
- Battery storage project AE2-331, Defiance CountyBattery storage Β· 139 MW Β· withdrawn
- Gas project AH1-735, Defiance CountyGas Β· 55.0 MW Β· withdrawn
- Solar project AF2-127, Defiance CountySolar Β· 38.0 MW Β· withdrawn
- Gas project Z1-021, Defiance CountyGas Β· 36.0 MW Β· withdrawn
- Battery storage project AF1-047, Defiance CountyBattery storage Β· 34.8 MW Β· withdrawn
- Solar project AF1-063, Defiance CountySolar Β· 30.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem