United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

Travis Kimbro BESS

Travis Kimbro BESS is a 36.8 MW battery storage request withdrawn in the ERCOT interconnection queue, in Travis County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2022 (completed)
  2. Withdrawn / abandonedDec 2025 (project stopped here)
  3. ConsentedOct 2024 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
24INR0330
Grid region
ERCOT (Texas)
Developer
Travis Kimbro BESS LLC
Connection point (POI)
7337 Kimbro 138kV
Location
Travis County, Texas
Technology
Battery: 36.8 MW
Total requested
36.8 MW
Study phase
IA and FIS Pending
Queue status
Withdrawn
Entered queue
1 September 2022
Agreement signed
31 October 2024
Proposed online date
September 2028
Withdrawn
December 2025

Location

Marker shows the centre of Travis County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Travis County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem