San Diego Wind #2 - Phase I

San Diego Wind #2 - Phase I is a 36.0 MW onshore wind request withdrawn in the CAISO interconnection queue, in San Diego County, California, connecting to SDGE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2004 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
26
Grid region
CAISO (California)
Utility / transmission owner
SDGE
Connection point (POI)
Crestwood
Location
San Diego County, California
Technology
Wind: 36.0 MW
Total requested
36.0 MW
Queue status
Withdrawn
Entered queue
12 February 2004
Proposed online date
January 2008

Location

Marker shows the centre of San Diego County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in San Diego County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem