United States › Grid › Interconnection queues › New York
BATTERY STORAGE · NYISOMorrow Street Energy Storage
Morrow Street Energy Storage is a 38.0 MW battery storage request withdrawn in the NYISO interconnection queue, in Richmond County, New York, connecting to ConEd.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2021 (completed)
- Withdrawn / abandonedAug 2021 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 1204
- Grid region
- NYISO (New York)
- Utility / transmission owner
- ConEd
- Developer
- Morrow Street Storage 2, LLC
- Connection point (POI)
- Goethals Substation
- Location
- Richmond County, New York
- Technology
- Battery: 38.0 MW
- Total requested
- 38.0 MW
- Queue status
- Withdrawn
- Entered queue
- 15 June 2021
- Withdrawn
- August 2021
Location
Marker shows the centre of Richmond County; the queue data does not give exact sites.
Other requests in Richmond County
- Resilient NY Energy StorageBattery storage · 349 MW · in study
- Elevate Arthur Kill IIBattery storage · 180 MW · in study
- Arthur Kill Energy Storage 1Battery storage · 15.0 MW · in study
- Atlantic Shores Offshore Wind Bight 2Offshore wind · 2,100 MW · withdrawn
- Atlantic Shores Offshore Wind Bight 5Offshore wind · 2,100 MW · withdrawn
- Agr NY-2Offshore wind · 1,600 MW · withdrawn
- Blue Point Wind 3AOnshore wind · 1,310 MW · withdrawn
- Bluepoint Wind 3BOnshore wind · 1,310 MW · withdrawn
- Community OSW Goethals 1Offshore wind · 1,100 MW · withdrawn
- NY Interconnection 6Offshore wind · 1,050 MW · withdrawn
- Atlantic Shores Offshore Wind 9Offshore wind · 880 MW · withdrawn
- Swiftsure Energy StorageBattery storage · 650 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem