OFFSHORE WIND Β· NYISOAgr NY-2
Agr NY-2 is a 1,600 MW offshore wind request withdrawn in the NYISO interconnection queue, in Richmond County, New York, connecting to ConEd.
Queue statusWithdrawn / abandoned
- PlanningQueued Feb 2022 (completed)
- Withdrawn / abandonedApr 2022 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 1332
- Grid region
- NYISO (New York)
- Utility / transmission owner
- ConEd
- Developer
- Avangrid Renewables
- Connection point (POI)
- Goethals 345 kV Substation
- Location
- Richmond County, New York
- Technology
- Offshore Wind: 1,600 MW
- Total requested
- 1,600 MW
- Queue status
- Withdrawn
- Entered queue
- 17 February 2022
- Withdrawn
- April 2022
Location
Marker shows the centre of Richmond County; the queue data does not give exact sites.
Other requests in Richmond County
- Resilient NY Energy StorageBattery storage Β· 349 MW Β· in study
- Elevate Arthur Kill IIBattery storage Β· 180 MW Β· in study
- Arthur Kill Energy Storage 1Battery storage Β· 15.0 MW Β· in study
- Atlantic Shores Offshore Wind Bight 2Offshore wind Β· 2,100 MW Β· withdrawn
- Atlantic Shores Offshore Wind Bight 5Offshore wind Β· 2,100 MW Β· withdrawn
- Blue Point Wind 3AOnshore wind Β· 1,310 MW Β· withdrawn
- Bluepoint Wind 3BOnshore wind Β· 1,310 MW Β· withdrawn
- Community OSW Goethals 1Offshore wind Β· 1,100 MW Β· withdrawn
- NY Interconnection 6Offshore wind Β· 1,050 MW Β· withdrawn
- Atlantic Shores Offshore Wind 9Offshore wind Β· 880 MW Β· withdrawn
- Swiftsure Energy StorageBattery storage Β· 650 MW Β· withdrawn
- Fresh Kills Energy StorageBattery storage Β· 500 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem