United States › Grid › Interconnection queues › New York

BATTERY STORAGE · NYISO

Arthur Kill Energy Storage 1

Arthur Kill Energy Storage 1 is a 15.0 MW battery storage request in interconnection study in the NYISO interconnection queue, in Richmond County, New York, connecting to ConEd.

Queue statusIn planning
  1. PlanningQueued Apr 2019 (current stage)
  2. ConsentedJul 2022 (not yet reached)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
827
Grid region
NYISO (New York)
Utility / transmission owner
ConEd
Developer
Lighthouse Arthur Kill, LLC
Connection point (POI)
Fresh Kills 13.8kV
Location
Richmond County, New York
Technology
Battery: 15.0 MW
Total requested
15.0 MW
Study phase
FS
Queue status
Active
Entered queue
22 April 2019
Agreement signed
7 July 2022

Location

Marker shows the centre of Richmond County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Richmond County