πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Washington

GAS Β· WEST

01 37MW Connell

01 37MW Connell is a 37.0 MW gas request withdrawn in the West interconnection queue, in Franklin County, Washington, connecting to Effective Energy Corporation.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2001 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G70-01
Grid region
West (non-ISO utilities)
Utility / transmission owner
Effective Energy Corporation
Developer
Effective Energy Corporation
Connection point (POI)
BPA's Connell Substation
Location
Franklin County, Washington
Technology
Gas: 37.0 MW
Total requested
37.0 MW
Service type
Energy only (ERIS)
Queue status
Withdrawn
Entered queue
14 August 2001
Proposed online date
June 2002

Location

Marker shows the centre of Franklin County; the queue data does not give exact sites.

Power plants in Washington Β· Transmission lines in Washington

Other requests in Franklin County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem