SOLAR Β· WEST

Solar project G0564, Franklin County

Solar project G0564, Franklin County is a 80.0 MW solar request withdrawn in the West interconnection queue, in Franklin County, Washington.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2017 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G0564
Grid region
West (non-ISO utilities)
Connection point (POI)
A line tap on BPA's Hatton Tap - Hatton 115 kV transmission line.
Location
Franklin County, Washington
Technology
Solar: 80.0 MW
Total requested
80.0 MW
Service type
NRIS and ERIS
Queue status
Withdrawn
Entered queue
23 May 2017
Proposed online date
June 2019

Location

Marker shows the centre of Franklin County; the queue data does not give exact sites.

Power plants in Washington Β· Transmission lines in Washington

Other requests in Franklin County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem