United States › Grid › Interconnection queues › Nevada
GEOTHERMAL · CAISOTungsten Mountain Geothermal Project
Tungsten Mountain Geothermal Project is a 38.0 MW geothermal request withdrawn in the CAISO interconnection queue, in Churchill County, Nevada, connecting to SCE.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2011 (completed)
- Withdrawn / abandonedMar 2012 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 774
- Grid region
- CAISO (California)
- Utility / transmission owner
- SCE
- Connection point (POI)
- Control Substation 115 kV bus
- Location
- Churchill County, Nevada
- Technology
- Geothermal: 38.0 MW
- Total requested
- 38.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- System Impact Study
- Queue status
- Withdrawn
- Entered queue
- 31 March 2011
- Proposed online date
- December 2013
- Withdrawn
- March 2012
Location
Marker shows the centre of Churchill County; the queue data does not give exact sites.
Other requests in Churchill County
- Solar + storage project Company MI, Churchill CountySolar + storage · 700 MW · agreement signed
- Solar + storage project Company JK, Churchill CountySolar + storage · 500 MW · agreement signed
- Solar + storage project Company MH, Churchill CountySolar + storage · 300 MW · agreement signed
- Solar + storage project Company JE, Churchill CountySolar + storage · 125 MW · agreement signed
- Geothermal project Company EV, Churchill CountyGeothermal · 38.5 MW · agreement signed
- Geothermal project Company KZ, Churchill CountyGeothermal · 38.5 MW · agreement signed
- Geothermal project Company HU, Churchill CountyGeothermal · 38.5 MW · agreement signed
- Geothermal project 25-00406, Churchill CountyGeothermal · 600 MW · in study
- Geothermal project 25-00409, Churchill CountyGeothermal · 600 MW · in study
- Solar + storage project Company QX, Churchill CountySolar + storage · 240 MW · in study
- Geothermal project 25-00405, Churchill CountyGeothermal · 200 MW · in study
- Geothermal project 25-00408, Churchill CountyGeothermal · 200 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem