SOLAR Β· CAISO

Del Sur Solar

Del Sur Solar is a 38.0 MW solar request withdrawn in the CAISO interconnection queue, in Los Angeles County, California, connecting to SCE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2011 (completed)
  2. Withdrawn / abandonedApr 2012 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
693
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Del Sur Substation 66kV Bus
Location
Los Angeles County, California
Technology
Solar: 38.0 MW
Total requested
38.0 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
31 March 2011
Proposed online date
March 2013
Withdrawn
April 2012

Location

Marker shows the centre of Los Angeles County; the queue data does not give exact sites.

Power plants in California Β· Transmission lines in California

Other requests in Los Angeles County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem