πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

SOLAR Β· ERCOT

Cabeza de Vaca

Cabeza de Vaca is a 37.8 MW solar request withdrawn in the ERCOT interconnection queue, in Lamar County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2021 (completed)
  2. Withdrawn / abandonedAug 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
24INR0074
Grid region
ERCOT (Texas)
Developer
PREMIER ENGINEERING USA CORP
Connection point (POI)
1788 Brookston 69kV
Location
Lamar County, Texas
Technology
Solar: 37.8 MW
Total requested
37.8 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
2 December 2021
Proposed online date
February 2026
Withdrawn
August 2024

Location

Marker shows the centre of Lamar County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Lamar County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem