United States βΊ Grid βΊ Interconnection queues βΊ Virginia
SOLAR + STORAGE Β· PJMSolar + storage project AG2-605, Amherst County
Solar + storage project AG2-605, Amherst County is a 37.0 MW solar + storage request withdrawn in the PJM interconnection queue, in Amherst County, Virginia, connecting to AEP.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2021 (completed)
- Withdrawn / abandonedOct 2024 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AG2-605
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Skimmer - Abert 69 kV
- Location
- Amherst County, Virginia
- Technology
- Solar: 37.0 MW Β· Battery
- Total requested
- 37.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 31 March 2021
- Proposed online date
- June 2024
- Withdrawn
- October 2024
Location
Marker shows the centre of Amherst County; the queue data does not give exact sites.
Other requests in Amherst County
- Amherst SolarSolar Β· 50.0 MW Β· agreement signed
- Battery storage project AI2-227, Amherst CountyBattery storage Β· 30.0 MW Β· in study
- Solar project AI2-345, Amherst CountySolar Β· 18.0 MW Β· in study
- Solar project AH2-137, Amherst CountySolar Β· 10.0 MW Β· in study
- Solar project AG1-123, Amherst CountySolar Β· 65.0 MW Β· withdrawn
- Mainspring GridBattery storage Β· 50.0 MW Β· withdrawn
- Battery storage project AG2-187, Amherst CountyBattery storage Β· 40.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem