Roundhouse Renewable

Roundhouse Renewable is a 36.0 MW gas request withdrawn in the NYISO interconnection queue, in Otsego County, New York, connecting to NYSEG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2006 (completed)
  2. Withdrawn / abandonedSep 2006 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
208
Grid region
NYISO (New York)
Utility / transmission owner
NYSEG
Developer
CRC Development, LLC
Connection point (POI)
City of Oneonta
Location
Otsego County, New York
Technology
Gas: 36.0 MW
Total requested
36.0 MW
Queue status
Withdrawn
Entered queue
17 January 2006
Withdrawn
September 2006

Location

Marker shows the centre of Otsego County; the queue data does not give exact sites.