United States βΊ Grid βΊ Interconnection queues βΊ New York
ONSHORE WIND Β· NYISOSmokey Ave Wind
Smokey Ave Wind is a 18.0 MW onshore wind request withdrawn in the NYISO interconnection queue, in Otsego County, New York.
Queue statusWithdrawn / abandoned
- PlanningQueued Dec 2020 (completed)
- Withdrawn / abandonedMay 2021 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 1124
- Grid region
- NYISO (New York)
- Developer
- Liberty Renewables
- Connection point (POI)
- Worcester - Schenevus 23 kV
- Location
- Otsego County, New York
- Technology
- Wind: 18.0 MW
- Total requested
- 18.0 MW
- Queue status
- Withdrawn
- Entered queue
- 22 December 2020
- Withdrawn
- May 2021
Location
Marker shows the centre of Otsego County; the queue data does not give exact sites.
Other requests in Otsego County
- West LaurensSolar Β· 350 MW Β· withdrawn
- West LaurensSolar Β· 350 MW Β· withdrawn
- Cherry Valley Wind PowerOnshore wind Β· 70.0 MW Β· withdrawn
- Roundhouse RenewableGas Β· 36.0 MW Β· withdrawn
- Monticello Hills WindOnshore wind Β· 31.5 MW Β· withdrawn
- Monticello Hills WindOnshore wind Β· 19.8 MW Β· withdrawn
- Smokey Avenue WindOnshore wind Β· 18.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem