HYDRO Β· MISO

Hydro project J2831, Natchitoches Parish County

Hydro project J2831, Natchitoches Parish County is a 36.0 MW hydro request withdrawn in the MISO interconnection queue, in Natchitoches Parish County, Louisiana, connecting to CLECO POWER.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2022 (completed)
  2. Withdrawn / abandonedJul 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2831
Grid region
MISO (Midcontinent)
Utility / transmission owner
CLECO POWER
Connection point (POI)
Colfax-Rodemacher 230 kV
Location
Natchitoches Parish County, Louisiana
Technology
Hydro: 36.0 MW
Total requested
36.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
15 September 2022
Proposed online date
April 2027
Withdrawn
July 2025

Location

Marker shows the centre of Natchitoches Parish County; the queue data does not give exact sites.

Power plants in Louisiana Β· Transmission lines in Louisiana

Other requests in Natchitoches Parish County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem