United States βΊ Grid βΊ Interconnection queues βΊ New York
SOLAR Β· NYISOThor Solar
Thor Solar is a 36.6 MW solar request withdrawn in the NYISO interconnection queue, in Rensselaer County, New York, connecting to Transco.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2024 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- C24-186
- Grid region
- NYISO (New York)
- Utility / transmission owner
- Transco
- Developer
- Blue Stone Renewable III
- Connection point (POI)
- Schodack - Falls Park 115kV
- Location
- Rensselaer County, New York
- Technology
- Solar: 36.6 MW
- Total requested
- 36.6 MW
- Queue status
- Withdrawn
- Entered queue
- 18 September 2024
Location
Marker shows the centre of Rensselaer County; the queue data does not give exact sites.
Other requests in Rensselaer County
- Willard Storage (NYISO-C24-148)Battery storage Β· 300 MW Β· in study
- Willard StorageBattery storage Β· 300 MW Β· in study
- SolarSolar Β· 20.0 MW Β· in study
- Hilltop SolarSolar Β· 20.0 MW Β· in study
- CS Hawthorn SolarSolar Β· 20.0 MW Β· in study
- Empire GeneratingGas Β· 635 MW Β· built
- Empire GeneratingGas Β· 635 MW Β· built
- StephentownBattery storage Β· 20.0 MW Β· built
- StephentownBattery storage Β· 20.0 MW Β· built
- Knickerbocker Energy StorageBattery storage Β· 300 MW Β· withdrawn
- Topaz Storage ProjectBattery storage Β· 200 MW Β· withdrawn
- Honey Bee Battery Storage, LLCBattery storage Β· 199 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem