United States › Grid › Interconnection queues › New York

SOLAR · NYISO

Hilltop Solar

Hilltop Solar is a 20.0 MW solar request in interconnection study in the NYISO interconnection queue, in Rensselaer County, New York, connecting to NM-NG.

Queue statusIn planning
  1. PlanningQueued Mar 2019 (current stage)
  2. ConsentedApr 2021 (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget May 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
807
Grid region
NYISO (New York)
Utility / transmission owner
NM-NG
Developer
SunEast Hilltop Solar LLC
Connection point (POI)
Eastover - Schaghticoke 115kV
Location
Rensselaer County, New York
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Study phase
SIS, FS
Queue status
Active
Entered queue
28 March 2019
Agreement signed
7 April 2021
Proposed online date
May 2028

Location

Marker shows the centre of Rensselaer County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Rensselaer County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem