United States βΊ Grid βΊ Interconnection queues βΊ New Mexico
OTHER Β· WESTOther project IA-PNM-2004-02, Torrance County
Other project IA-PNM-2004-02, Torrance County is a 37.0 MW other request withdrawn in the West interconnection queue, in Torrance County, New Mexico, connecting to Public Service Company of New Mexico.
Queue statusWithdrawn / abandoned
- PlanningQueued Jul 2004 (completed)
- Withdrawn / abandoned (project stopped here)
- ConsentedDec 2009 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- IA-PNM-2004-02
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Public Service Company of New Mexico
- Connection point (POI)
- Western Water and Power
- Location
- Torrance County, New Mexico
- Technology
- Other: 37.0 MW
- Total requested
- 37.0 MW
- Study phase
- LGIA Terminated 4/9/24.
- Queue status
- Withdrawn
- Entered queue
- 20 July 2004
- Agreement signed
- 16 December 2009
- Proposed online date
- March 2012
Location
Marker shows the centre of Torrance County; the queue data does not give exact sites.
Power plants in New Mexico Β· Transmission lines in New Mexico
Other requests in Torrance County
- Onshore wind project IA-PNM-2016-02, Torrance Cty CountyOnshore wind Β· 402 MW Β· agreement signed
- Onshore wind project IA-PNM-2025-19, Torrance CountyOnshore wind Β· 400 MW Β· in study
- Onshore wind project IA-PNM-2025-18, Torrance CountyOnshore wind Β· 250 MW Β· in study
- Onshore wind project IA-PNM-2019-12, Torrance CountyOnshore wind Β· 80.0 MW Β· in study
- Solar + storage project IA-PNM-2017-11, Torrance CountySolar + storage Β· 74.9 MW Β· in study
- Onshore wind project IA-PNM-2007-10, Torrance CountyOnshore wind Β· 700 MW Β· built
- Onshore wind project IA-PNM-2018-04, Torrance CountyOnshore wind Β· 674 MW Β· built
- Tecolote WindOnshore wind Β· 272 MW Β· built
- Duran MesaOnshore wind Β· 105 MW Β· built
- Onshore wind project IA-PNM-2006-02, Torrance Cty CountyOnshore wind Β· 100 MW Β· built
- NMRD Data Center IISolar Β· 60.0 MW Β· built
- Onshore wind project IA-PNM-2019-06, Torrance CountyOnshore wind Β· 700 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem