United States › Grid › Interconnection queues › New Mexico

ONSHORE WIND · WEST

Tecolote Wind

Tecolote Wind is a 272 MW onshore wind request built and operating in the West interconnection queue, in Torrance County, New Mexico, connecting to Public Service Company of New Mexico.

Queue statusOperating
  1. PlanningQueued Apr 2019 (completed)
  2. ConsentedAug 2020 (completed)
  3. Construction (completed)
  4. OperatingTarget Sep 2020 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
IA-PNM-2019-24
Grid region
West (non-ISO utilities)
Utility / transmission owner
Public Service Company of New Mexico
Connection point (POI)
Western Spirit 345 kV Switching Station
Location
Torrance County, New Mexico
Technology
Wind: 272 MW
Total requested
272 MW
Service type
Energy only (ERIS)
Study phase
Provisional Interconnection Agreement (PIA) executed 8/25/2020. PIA superseded by LGIA executed 6/13/24.
Queue status
Operational
Entered queue
23 April 2019
Agreement signed
25 August 2020
Proposed online date
September 2020

Location

Marker shows the centre of Torrance County; the queue data does not give exact sites.

Power plants in New Mexico · Transmission lines in New Mexico

Other requests in Torrance County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem