United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Battery storage interconnection queue in the USA — page 28

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,226417.8 GW
Active in queue417.8 GW2,226 requests
Agreement signed76.1 GW459 requests
Withdrawn3,516554.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,226 requests · page 28 of 45
ProjectCapacityStatusLocationRegionQueuedOnline
Salazar BESS
Battery storage · Salazar Energy Storage LLC
128 MWIn study Tarrant, TXERCOT Oct 2024target 2028
Battery storage project 112, Thurston County
Battery storage
127 MWAgreement signed Thurston, WAWest Jun 2021target 2029
Solar Star North Herty Storage
Battery storage · Solar Star North Herty Storage, LLC
126 MWIn study Angelina, TXERCOT Feb 2022target 2027
Dolomite Storage
Battery storage · BT Wilson Storage, LLC
126 MWIn study Ellis, TXERCOT Sep 2023target 2026
Benitoite Storage
Battery storage · BT Van Storage, LLC
126 MWIn study Van Zandt, TXERCOT Mar 2024target 2027
Zodiac Storage
Battery storage · Grenergy USA
126 MWIn study Val Verde, TXERCOT Nov 2024target 2028
Becerra Creek Storage 1
Battery storage · Bordas Renewable Energy, LLC
126 MWIn study Webb, TXERCOT Sep 2022target 2027
Spinner Energy Storage
Battery storage · GCI Wolf Energy Storage, LLC
126 MWIn study Bee, TXERCOT Oct 2023target 2027
Becerra Creek Storage 2
Battery storage · Bordas Renewable Energy, LLC
126 MWIn study Webb, TXERCOT Sep 2022target 2027
Momentum Hazy Jane BESS
Battery storage · MOMENTUM HAZY JANE, LLC
126 MWIn study Ector, TXERCOT Nov 2023target 2028
Momentum Stout BESS
Battery storage · Momentum STOUT, LLC
126 MWIn study Burnet, TXERCOT Nov 2023target 2027
Momentum Bock
Battery storage · Momentum Bock, LLC
125 MWIn study Lamar, TXERCOT Sep 2024target 2028
TE Smith Storage
Battery storage · BT Smith Storage, LLC
125 MWAgreement signed Rockwall, TXERCOT Sep 2021target 2026
Jumping Cactus Storage
Battery storage · Dove Run Solar Project, LLC
125 MWIn study Duval, TXERCOT Jan 2024target 2028
Saluga Ranch Storage
Battery storage · Saluga Ranch Energy, LLC
125 MWIn study Dimmit, TXERCOT Feb 2024target 2027
Houston County BESS
Battery storage · Houston ESS, LLC
125 MWIn study Houston, TXERCOT Feb 2024target 2027
TE Smith Storage 2
Battery storage · Smith II Battery Storage, LLC
125 MWIn study Rockwall, TXERCOT Apr 2024target 2027
Project Lynx BESS
Battery storage · Corpus Battery Storage, LLC
125 MWAgreement signed Nueces, TXERCOT Mar 2023target 2026
Battery Storage
Battery storage
125 MWIn study Middlesex, MAISO-NE Jun 2024target 2028
Battery storage project 21-11153, Boulder County
Battery storage
125 MWIn study Boulder, COWest Nov 2021target 2027
Leconte Energy Storage
Battery storage
125 MWAgreement signed Imperial, CACAISO Apr 2015target 2026
Battery storage project LGE-CS2025-003, Crittenden County
Battery storage
125 MWIn study Crittenden, KYSoutheast Dec 2025target 2029
Battery storage project GI-2021-145, Riverside County
Battery storage
125 MWIn study Riverside, CAWest Aug 2021target 2027
Battery storage project LGE-GIS-2023-003, Mercer County
Battery storage
125 MWIn study Mercer, KYSoutheast Apr 2023target 2026
Battery storage project AH2-084, Fauquier County
Battery storage
125 MWIn study Fauquier, VAPJM Jan 2022target 2027
Battery storage project J1358, Laporte County
Battery storage
125 MWAgreement signed Laporte, INMISO Apr 2019target 2026
East Setauket Energy Storage
Battery storage · East Setauket Energy Storage, LLC
125 MWIn study Suffolk, NYNYISO Jan 2020target 2027
Battery storage project Company JP, Washoe County
Battery storage
125 MWAgreement signed Washoe, NVWest Sep 2018target 2027
Battery storage project 21-11157, Larimer County
Battery storage
125 MWIn study Larimer, COWest Nov 2021target 2026
Battery storage project Q423, Navajo County
Battery storage
125 MWIn study Navajo, AZWest Sep 2021target 2025
Battery storage project 121, King County
Battery storage
125 MWPaused / redesign King, WAWest Aug 2021target 2030
Battery storage project Q384, Maricopa County
Battery storage
125 MWPaused / redesign Maricopa, AZWest Mar 2021target 2025
Battery storage project GEN-2024-251, Eddy County
Battery storage
125 MWIn study Eddy, NMSPP Mar 2025target 2029
Battery storage project GEN-2023-SR22, Mayes County
Battery storage
125 MWIn study Mayes, OKSPP Jun 20232024
El Rey Power Bank
Battery storage
124 MWIn study Monterey, CACAISO Apr 2021target 2029
Ajo Power Bank
Battery storage
124 MWAgreement signed Santa Clara, CACAISO Apr 2018target 2028
Backbone Creek BESS
Battery storage · Backbone Creek BESS LLC
124 MWAgreement signed Burnet, TXERCOT Apr 2022target 2026
Bonita Bateria 2
Battery storage
123 MWIn study Orange, CACAISO Apr 2023target 2029
Sleepy Hollow BESS
Battery storage · Sleepy Hollow BESS, LLC
123 MWIn study Throckmorton, TXERCOT Nov 2023target 2028
Battery storage project ERAS-2025-022, Pontotoc County
Battery storage
123 MWIn study Pontotoc, OKSPP Oct 2025target 2028
Great Hambino BESS
Battery storage · Atascosa BESS, LLC
123 MWIn study Atascosa, TXERCOT Sep 2025target 2027
Signal Hill BESS I
Battery storage · Signal Hill Generating LLC
123 MWIn study Wichita, TXERCOT Sep 2024target 2027
East West BESS
Battery storage · East West Energy Storage, LLC
123 MWAgreement signed Kerr, TXERCOT Oct 2022target 2027
Prairie Blossom Storage
Battery storage · Prairie Blossom Storage, LLC
123 MWIn study Howard, TXERCOT Dec 2024target 2028
Arnold Hills Storage
Battery storage · Arnold Hills Storage, LLC
123 MWIn study Henderson, TXERCOT Mar 2025target 2029
Dove Wing Storage
Battery storage · Dove Run Solar Project, LLC
122 MWIn study Duval, TXERCOT Feb 2024target 2028
Battery storage project S0033, Washington County
Battery storage
122 MWIn study Washington, UTWest Dec 2024target 2027
BRP Ampato BESS
Battery storage · BRP Ampato BESS LLC
122 MWIn study Crane, TXERCOT Aug 2020target 2027
Wildhorse Energy Center
Battery storage
122 MWIn study Sonoma, CACAISO Apr 2021target 2030
Marengo BESS
Battery storage · BRP BLUE TOPAZ 8, LLC
121 MWIn study Cameron, TXERCOT May 2023target 2028
Page 28 of 45

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)