Solar Star North Herty Storage

Solar Star North Herty Storage is a 126 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Angelina County, Texas.

Queue statusIn planning
  1. PlanningQueued Feb 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Aug 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
24INR0174
Grid region
ERCOT (Texas)
Developer
Solar Star North Herty Storage, LLC
Connection point (POI)
3307 Redland Switch 138 kV
Location
Angelina County, Texas
Technology
Battery: 126 MW
Total requested
126 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
21 February 2022
Proposed online date
August 2027

Location

Marker shows the centre of Angelina County; the queue data does not give exact sites.