BATTERY STORAGE Β· ERCOT

Kruth Storage

Kruth Storage is a 203 MW battery storage request withdrawn in the ERCOT interconnection queue, in Angelina County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2022 (completed)
  2. Withdrawn / abandonedNov 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
24INR0252
Grid region
ERCOT (Texas)
Developer
Martinez Energy Storage LLC
Connection point (POI)
3319 Redland 138kV
Location
Angelina County, Texas
Technology
Battery: 203 MW
Total requested
203 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
27 February 2022
Proposed online date
March 2026
Withdrawn
November 2025

Location

Marker shows the centre of Angelina County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Angelina County