Jefferson Enterprise Energy

Jefferson Enterprise Energy is a 53.0 MW other request withdrawn in the ERCOT interconnection queue, in Angelina County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2021 (completed)
  2. Withdrawn / abandonedFeb 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
21INR0543
Grid region
ERCOT (Texas)
Developer
ONCOR
Connection point (POI)
3118 LUFKIN SWITCH 138kV
Location
Angelina County, Texas
Technology
Other: 53.0 MW
Total requested
53.0 MW
Study phase
FIS Complete
Queue status
Withdrawn
Entered queue
23 September 2021
Proposed online date
April 2025
Withdrawn
February 2024

Location

Marker shows the centre of Angelina County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Angelina County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem