United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

Salazar BESS

Salazar BESS is a 128 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Tarrant County, Texas.

Queue statusIn planning
  1. PlanningQueued Oct 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jul 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
28INR0116
Grid region
ERCOT (Texas)
Developer
Salazar Energy Storage LLC
Connection point (POI)
2068 Rosen Heights 138kV
Location
Tarrant County, Texas
Technology
Battery: 128 MW
Total requested
128 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
1 October 2024
Proposed online date
July 2028

Location

Marker shows the centre of Tarrant County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Tarrant County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem