United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

Stockyard Grid Batt

Stockyard Grid Batt is a 151 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Tarrant County, Texas.

Queue statusConsented
  1. PlanningQueued Jan 2020 (completed)
  2. ConsentedOct 2022 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
21INR0492
Grid region
ERCOT (Texas)
Developer
Stockyard Grid, LLC
Connection point (POI)
2082 Hicks 138kV
Location
Tarrant County, Texas
Technology
Battery: 151 MW
Total requested
151 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
13 January 2020
Agreement signed
26 October 2022
Proposed online date
December 2026

Location

Marker shows the centre of Tarrant County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Tarrant County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem