United States › Grid › Interconnection queues › Texas
BATTERY STORAGE · ERCOTStockyard Grid Batt
Stockyard Grid Batt is a 151 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Tarrant County, Texas.
Queue statusConsented
- PlanningQueued Jan 2020 (completed)
- ConsentedOct 2022 (current stage)
- Construction (not yet reached)
- OperatingTarget Dec 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 21INR0492
- Grid region
- ERCOT (Texas)
- Developer
- Stockyard Grid, LLC
- Connection point (POI)
- 2082 Hicks 138kV
- Location
- Tarrant County, Texas
- Technology
- Battery: 151 MW
- Total requested
- 151 MW
- Study phase
- SS Completed, FIS Completed, IA
- Queue status
- Active
- Entered queue
- 13 January 2020
- Agreement signed
- 26 October 2022
- Proposed online date
- December 2026
Location
Marker shows the centre of Tarrant County; the queue data does not give exact sites.
Other requests in Tarrant County
- Meadow Park BESSBattery storage · 10.0 MW · agreement signed
- Nabla Energy Storage IBattery storage · 750 MW · in study
- Team Ranch StorageBattery storage · 307 MW · in study
- Anglin BESSBattery storage · 206 MW · in study
- Salazar BESSBattery storage · 128 MW · in study
- Chisholm GridOther · 102 MW · built
- Century BESSOther · 9.9 MW · built
- Firefly PowerBattery storage · 401 MW · withdrawn
- Fort Watt StorageBattery storage · 205 MW · withdrawn
- Onshore wind project GEN-2004-001, Tarrant CountyOnshore wind · 200 MW · withdrawn
- Solar Star Western Hills StorageOther · 160 MW · withdrawn
- Elmer BatteryOther · 100 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem