Meadow Park BESS

Meadow Park BESS is a 10.0 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Tarrant County, Texas.

Queue statusConsented
  1. PlanningQueued Jun 2025 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Feb 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
26INR0699
Grid region
ERCOT (Texas)
Developer
Meadow Park ESS Assets, LLC
Connection point (POI)
Station Name: Meadow Park | Oncor 5-digit code: MDWPK | Oncor XFMR Number: 2 | ERCOT Bus Name: MEADPRK1_8 | ERCOT Bus#: 2039 | ERCOT Load Name: LDLXFMR2 | Substation Transmission kV: 138 kV | ERCOT No
Location
Tarrant County, Texas
Technology
Battery: 10.0 MW
Total requested
10.0 MW
Study phase
MRD Approved
Queue status
Active
Entered queue
19 June 2025
Proposed online date
February 2026

Location

Marker shows the centre of Tarrant County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Tarrant County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem