| Project | Capacity | Status |
|---|---|---|
| Hecate Solar Solar · Hecate Energy |
33.0 MW | Paused / redesign |
| Weathervane Storage SLF Battery storage |
32.5 MW | Paused / redesign |
| Meridian BESS Battery storage · Navitas Energy- Meredian BESS |
31.2 MW | In study |
| Lager Storage Battery storage · Momentum Lager LLC |
31.1 MW | In study |
| Hooper Storage Solar + storage · BT Brown Solar, LLC |
30.7 MW | In study |
| M-Bar Solar I Solar + storage · M-Bar Energy I, LLC |
30.2 MW | In study |
| Half Moon Battery Battery storage |
30.2 MW | Paused / redesign |
| Spinel Solar Solar |
30.0 MW | Paused / redesign |
| Hillboro Wind Wind + storage · Abei Energy Green XI LLC |
27.8 MW | In study |
| Zeus Rusk Solar Solar + storage · Rusk Solar, LLC |
26.8 MW | In study |
| Fowler Ranch Storage Battery storage · Crane BESS, LLC |
26.1 MW | In study |
| NET Power Demonstration plant Gas · NET Power LLC |
25.5 MW | In study |
| Kennedy Storage Solar + storage · Kennedy Bypass Solar LLC |
25.3 MW | In study |
| Burro Loco Energy Storage Battery storage · VESI |
25.1 MW | In study |
| Fluorite Solar Solar |
25.0 MW | Paused / redesign |
| Knickerbocker Storage Other · Knickerbocker Solar LLC |
25.0 MW | Paused / redesign |
| CPS Energy AvR1CT2 Rotor Replacement Gas · CPS Energy |
23.2 MW | In study |
| Brazos Wind Repower Onshore wind · BRAZOS WIND VENTURES, LLC |
22.4 MW | In study |
| Brandon Gas |
21.0 MW | Paused / redesign |
| Sparkl BESS Battery storage |
20.0 MW | Paused / redesign |
| Basalt Solar Solar |
20.0 MW | Paused / redesign |
| Shannon Wind Repower Onshore wind · Shannon Wind, LLC |
18.5 MW | In study |
| Buzzi Maryneal Wind Project Onshore wind · Buzzi Unicem USA |
18.0 MW | In study |
| Midlothian 4 repower Gas · MIDLOTHIAN ENERGY, LLC |
18.0 MW | In study |
| Midlothian Unit 2 repower Gas · MIDLOTHIAN ENERGY, LLC |
18.0 MW | In study |
| Hays Energy Unit 2 Repower Gas · HAYS ENERGY, LLC |
18.0 MW | In study |
| Hays Energy Unit 3 Repower Gas · HAYS ENERGY, LLC |
18.0 MW | In study |
| Midlothian Unit 3 repower Gas · MIDLOTHIAN ENERGY, LLC |
18.0 MW | In study |
| Clutch City Storage I SLF Battery storage |
16.6 MW | Paused / redesign |
| Texas Gulf Sulphur Repower Gas |
16.1 MW | Paused / redesign |
| Stephens Ranch Wind Repower Onshore wind · Stephens Ranch Wind Energy, LLC |
12.4 MW | In study |
| Clutch City Storage II SLF Battery storage |
11.3 MW | Paused / redesign |
| CPS AvR CT1 Rotor Replacement Gas · CPS Energy |
11.3 MW | In study |
| Panther Creek 1 Repower Onshore wind · Panther Creek Wind Farm I&II, LLC |
11.0 MW | In study |
| Mirage Gas |
11.0 MW | Paused / redesign |
| Bexar Martinez BESS Battery storage · Bexar Martinez LLC |
10.0 MW | In study |
| Slaton BESS Battery storage · Prairie Dog BESS, LLC |
10.0 MW | In study |
| Compton BESS Battery storage · SMT Dallas VII LLC |
10.0 MW | In study |
| Wildhorse POD Solar Solar · Highpeak Solar, LLC |
10.0 MW | Paused / redesign |
| Atascocita BESS Battery storage · SMT Houston XIV LLC |
10.0 MW | In study |
| Harris Spencer BESS Other · Harris Spencer BESS, LLC |
10.0 MW | Paused / redesign |
| Pleasanton BESS Other |
10.0 MW | Paused / redesign |
| Cuero BESS Battery storage · CUERO BESS, LLC |
10.0 MW | In study |
| Medina City BESS Battery storage · Regis Medina, LLC |
10.0 MW | In study |
| Juno Solar 3 Solar · SE JUNO LLC |
10.0 MW | Paused / redesign |
| Scenic Woods BESS Battery storage · SMT Houston V LLC |
10.0 MW | In study |
| Blue Summit repower Onshore wind |
9.9 MW | Paused / redesign |
| Chocolate Bayou BESS Battery storage · Concurrent Holdco. , LLC. |
9.9 MW | In study |
| Leakey BESS Battery storage · Regis Leaky LLC |
9.9 MW | In study |
| Panther Creek 2 Repower Onshore wind · Panther Creek Wind Farm I&II, LLC |
8.0 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)1,496 · 455.6 GW
- ERCOT (Texas)1,408 · 328.0 GW
- MISO (Midcontinent)1,337 · 302.2 GW
- Southeast (non-ISO utilities)815 · 118.5 GW
- SPP (Southwest Power Pool)480 · 114.8 GW
- PJM (Mid-Atlantic, Midwest)905 · 105.4 GW
- CAISO (California)194 · 92.4 GW
- NYISO (New York)190 · 27.1 GW
- ISO-NE (New England)27 · 6,015 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)