United States › Grid › Interconnection queues › Texas

GAS · ERCOT

Hays Energy Unit 2 Repower

Hays Energy Unit 2 Repower is a 18.0 MW gas request in interconnection study in the ERCOT interconnection queue, in Hays County, Texas.

Queue statusIn planning
  1. PlanningQueued Feb 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
22INR0586
Grid region
ERCOT (Texas)
Developer
HAYS ENERGY, LLC
Connection point (POI)
7043 Haysen 345kV
Location
Hays County, Texas
Technology
Gas: 18.0 MW
Total requested
18.0 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
21 February 2022
Proposed online date
December 2026

Location

Marker shows the centre of Hays County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Hays County