πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

SOLAR Β· ERCOT

Wildhorse POD Solar

Wildhorse POD Solar is a 10.0 MW solar request suspended in the ERCOT interconnection queue, in Howard County, Texas.

Queue statusPaused / redesign
  1. PlanningQueued Oct 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Feb 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
23INR0537
Grid region
ERCOT (Texas)
Developer
Highpeak Solar, LLC
Connection point (POI)
TDSP Station Code: WHPOD_x000D_ PTI BUS #: 1397_x000D_ Load/Load TR: LDWHPOD_x000D_ Voltage Level (Transmission): 138kV
Location
Howard County, Texas
Technology
Solar: 10.0 MW
Total requested
10.0 MW
Study phase
No MRD
Queue status
Suspended
Entered queue
2 October 2023
Proposed online date
February 2026

Location

Marker shows the centre of Howard County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Howard County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem